DELAY AND PROJECT DELIVERY IN ROAD CONSTRUCTION CONTRACTS BY NIGER DELTA DEVELOPMENT COMMISSION (NDDC) - 2019 TO 2024
Akwapoly Journal of Communication and Scientific Research (APJOCASR)
DOI:
https://doi.org/10.60787/apjcasr.Vol8No2.36Keywords:
Delay, Performance, Procurement, NDDC, Road Project,Abstract
Delays in road construction projects are a significant concern across various regions, impacting project delivery and overall success. This study examined the level of delay in road construction project delivery performed by the Niger Delta Development Commission (NDDC), Nigeria. The study adopted both quantitative and qualitative approaches, with secondary data obtained from consulting and contracting firms that have registered and are actually involved in the execution of NDDC road projects in the selected States of the Niger Delta region. The pilot survey revealed a total of one hundred and thirty-six (136) awarded and executed road projects from 33 consulting and 103 contracting firms and organizations, respectively. The total enumeration was adopted using a purposive sampling method, and projects awarded between 2019 and 2024 were considered. Data were analyzed using descriptive analysis and One-way ANOVA. The findings revealed a high level of delay, above two hundred percent (200%) average, on road projects executed by NDDC in Niger Delta regions. The test revealed no significant differences in the level of delay since the significant value was greater than 0.05; hence, the hypothesis was accepted. It follows that location has no effect on the level of delay experienced by the contractors involved in the road construction projects. The study concluded that road projects procured by the NDDC experienced excessive delay and recommended that the managers and directors of NDDC road projects should embark on proper contract appropriation, adopt accurate contract documentation, avoid a constant award of contracts to the same team, and prompt release of mobilization fees to parties concerned by the commission.
References
Alfakhri, A., Ismail, A., & Khoiry, A. M. (2018). The Effects of Delays in Road Construction Projects in Tripoli, Libya International Journal of Technology and Management https://doi.org/10.14716/IJTECH.V9I4.2219.
Alhinai, S., & Widyarto, S. A (2020). Conceptual Paper: Factors Causing Delays in
Roads Construction in Sultanate of Oman. Post Grad. Res. Symp. 1, 1.
Al-Kharashi, A., & Skitmore, M. (2009). Causes of Delays in Saudi Arabia Public Sector Construction Projects. Construction Management and Economics, 27 (1), 3-23.
Anoruo, E., & Barba, H. (2005). Corruption and Economic Growth, The African Experience, Journal of Sustainable Development in Africa 7(1), 43-55.
Agbu, O. (2005). Oil and Environmental Conflicts, in A. Hassan Saliu (ed) Nigeria under Democratic Rule, 1999–2003, .2, Ibadan: University Press.
Aysha, S., Hussain, A., Naveed, A., Muhammad, N., & Nouman, A. (2015). Analysis of key Performance Factors Affecting Residential Construction Projects in Pakistan Arabian Journal of Business and Management Review 3(10).
Aziz, R. F., & Abdel-Hakam, A. A. (2016) Exploring Delay Causes of Road Construction Projects in Egypt, Alexandria Engineering Journal, 55, 1515-1539. http://dx.doi.org/10.1016/j.aej.2016.03.006.
Chhotelal, B. Y., Tophique, Q., &, Hira Lal Yadav (2023). Study of Delays in Indian Road Construction Projects under Different Contracts I-manager's Journal on Structural Engineering. 12(1),34 https://doi.org/10.26634/jste.12.1.19974.
Dafinone, D. O. (2007). “The Niger Delta Crisis: Genesis the Exodus and the Solution”, Chairman’s Address in Niger Delta Peace Conference, Abuja, Nigeria.
Durdyev, S., & Hosseini, M. (2020). Causes of Delays on Construction Projects: a Comprehensive list, International Journal of Managing Projects in Business https://doi.org/10.1108/IJMPB-09-2018-0178.
Ekanem, S. F. (2019). Impact of Delay on the Performance of Road Projects Procured by Niger Delta Development Commission. unpublished thesis. Department of Quantity Surveying, Obafemi Awolowo University of Ile-Ife, Nigeria.
Ekanem, S, F., Jagboro, G.O., Akintayo, O., & Timothy, O. A. (2020). Modelling Delay of Road Construction Projects in ‘No Funding-Stress’ Scenario using Ordinal Logistic Regression Approach. Journal of Civil and Environmental Research. 12(9), 60-78. https://doi.org/10.7176/CER/12-9-07.
Hinai, S., Bhuiyan, A., & Setyawan Widyarto, (2020). The Empirical Review of Critical Success Factors on The Causes of Delay in Road Constructions Projects in The GCC Countries. Australian Finance & Banking Review,4(2),15-36, https://doi.org/10.46281/afbr.v4i2.920.
Kagiri, D. (2005). Time and Cost Overruns in Power Projects: A case Study of Kenya Electricity Generating Company. Unpublished MBA Project, University of Nairobi.
Khalid, K., Farouk, H., Mohamed, Z., & Mohammad, R. (2016). Causes and Effects of Delay Factors in Road Construction Projects in Sudan. International Journal of Applied Engineering Research ISSN 0973-4562 11(18), 9526-33.
Ludwig, R., Hilario, B., Jr. & Chunho, Y. (2020). A Study on Causes of Delay in Road Construction Projects Across 25 Developing Countries. International School of Urban Sciences, University of Seoul, Seoul 151-742, Korea; [email protected] (L.R.); [email protected] (H.B.J.)
Mahamid, I. (2018). Schedule Delay in Saudi Arabia Road Construction Projects: Size, Estimate, Determinants and Effects, https://doi.org/10.7492/IJAEC.2017.017.
Mahamid, I. (2017). Risk Matrix for Factors Affecting Time Delay in Road Construction Projects: Owners’ Perspective. Engineering Construction Architecture Management 18, 609–617.
Mahamid, 1., Bruland, A., & Dmaidi, N. (2012). Delay Causes in Road Construction Projects ASCE Journal of Management in Engineering 28(3), 300-310.
Mbala, M., Aigbavboa, C., & John Aliu (2020). Causes of Delay in Various Construction Projects: A Literature Review Advances in Human Factors, Sustainable Urban Planning and infrastructure https://doi.org/10.1007/978-3-319-94199-8_47.
Mike, O. (2015). The Nation: Anxieties in Bayelsa over #10 Billion Okoroba – Opume NDDC Road Project. w.waado.org/Niger Delta/Documents/Niger Delta Documents/ NNDCAct.html accessed March, 2024.
NDDC Act. (2000). Niger Delta Development Commission Act, No.2 www.waado.org/NigerDelta/Documents/NigerDeltaDocuments/NNDCAct.html
NDDC (2000). NDDC: History of the Commission. http://www.nddconline.org/history.shtml, 22/7/2024.
Niger Delta Development Commission (2009). NDDC http://www.nddc.gov.ng/ [Accessed April, 2024].
Ogunsemi, D. R. & Jagboro, G. O. (2006). Time-Cost Model for Building Projects in Nigeria Construction Management and Economics 24, 253-258.
Okumbe, J. & Verster, J. (2008). Construction Industry’s Perspective on Causes and Effects of Delays in South Africa. Available at: www. rics. org. [Accessed April, 2023]
Opawole, A (2015). Performance of Project Objectives in Donor Funded Infrastructure in Nigeria Universities, Journal of Nigerian Institute of Quantity Surveyors, 61(1), 21-27.
Opawole, A., Jagboro, G. O., Babalola, M. & Babatunde, S. (2013). Critical Factors in Road Infrastructure Development in Osun State, South-western, Nigeria. International Journal of Development and Sustainability 2(1), 240-253.
Ramanathan, C., Narayanan, S., & Idrus, A. B. (2012). Construction Delays Causing Risks On Time And Cost – a Critical Review, Australia . Journal Construction Economic Building 12 (1) 37–57.
Sanchez, O., Castaneda, K., Mejia, G., & Pellicer, E. (2020). Delay Factors: A Comparative Analysis between Road Infrastructure and Building Projects, American Society of Civil Engineering,223-231 https://doi.org/10.1061/9780784482889.024.
Shankar C, Saranya K, Col Jacob G Podipara, V. S. Srinithee (2021). Causes of Delay for
Construction Projects. Journal of University of Shanghai for Science and Technology, 23(9), 1073-77 https://doi.org/10.51201/jusst/21/09652.
Downloads
Published
Issue
Section
License
Copyright (c) 2024 Akwapoly Journal of Communication & Scientific Research
This work is licensed under a Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License.